VARIATION PROCEDURE CHECKLIST
-
PROPOSED VARIATION NOTICE
-
The Superintendent on behalf of the Principal issues the Contractor a written Notice of Proposed Variation
-
Contractor identifies whether the project can be effected
-
Contractor provides Superintendent will written quotation
-
Principal decides not to proceed and directs Contractor to continue with original scope or Principal accepts the variation price estimate and directs Contractor to proceed
-
DIRECTION TO EXECUTE VARIATION
-
Superintendent issues the Contractor a written Direction Notice
-
Contractor identifies whether the project cannot be effected
-
Contractor either approves or rejects variation
-
Contractor begins work
-
PRICING
-
Superintendent prices variation
-
Superintendent adds or deducts variation cost from original contract sum
-
Contractor claims progress payments in regular scehduled payemtns
-
WHEN THE PROPOSED VARIATION CAUSES A DELAY
-
As soon as possible once the Contractor becomes aware of possible delay they must give written notice to the Superintendent
-
If the project will result in a delay within 28 days the Contractor must lodge a written Extension of Time (EOT) claim
-
Superintendent either approves or rejects EOT claim