Bathroom Remodel in 7 Days
-
Day 1
-
Demo Preparation
See description -
#1Turn off water to home before starting Demo
See description -
#2 Remove Toilet
See description -
#3 Remove vanity top, disconnect plumbing, & remove old shut off valves
See description -
#4 Remove Vanity
See description -
#5 Cap water supplies
See description -
#6 Remove shower faucet trim
See description -
#7 Remove tub drain
See description -
#8 Cut and cap water supplies for faucet
See description -
#9 Remove Tub Surround
See description -
#10 Remove Tub
See description -
#11 Disconnect & remove light fixtures
See description -
#12 Remove all drywall or plaster
See description -
#13 Add temporary light fixture
See description -
#14 Remove Drywall Ceiling
See description -
#15 Remove existing vent fan
See description -
#16 Install new vent fan
See description -
#17 Run wire for recessed light above shower
See description -
#18 Hang Drywall ceiling
See description -
#19 Remove Floor
See description -
Day 2
-
#20 Remove existing trap
See description -
#21 Dryfit tub and Mark drain location
See description -
#22 Attach Fernco to existing plumbing
See description -
#23 Install new subfloor
See description -
#24 Install tub drain
See description -
Tubs I like and recommend
See description -
#25 Install tub drain assembly
See description -
#26 Dry fit tub and set ledger board
See description -
#27 Dry fit tub again 😊
See description -
#28 Set P-trap arm
See description -
#29 Set & secure tub in place
See description -
#30 Attach Trap to Drain assembly
See description -
#31 Adapt copper supplies to Pex
See description -
#32 Install rough-in shower valve
See description -
Tub/shower faucets I recommend
See description -
#33 Fill Tub and Test
See description -
#34 Move sink drain (if applicable)
See description -
#35 GFI outlet
See description -
Day 3
-
#36 Framing, blocking, shimming
See description -
#37 Blocking for Accessories
See description -
#38 Hanging Drywall
See description -
#39 1st coat drywall
See description -
#40 Tile Layout
See description -
#41 Frame niche
See description -
#42 Waterproof Backerboard for Tub Surround
See description -
#43 Valve & Pipe seals
See description -
Day 4
-
#44 Set Schluter Ditra for floor
See description -
#45 Waterproof against tub
See description -
#46 Waterproofing floor
See description -
#47 Tile Layout
See description -
#48 Determine trowel size
See description -
My favorite thinsets
See description -
#49 Check coverage
See description -
#50 Tile back wall of shower
See description -
#51 Cut shelving
See description -
#52 Tile side wall
See description -
Clean tiles
See description -
#53 2nd coat drywall
See description -
#54 Tile floor layout
See description -
#55 Cut and prepare floor tile
See description -
#56 Setting mosaics on Kerdi Band
See description -
Day 5
-
#57 Tile plumbing wall
See description -
#58 Tile Niche
See description -
#59 Set edging of Niche
See description -
#60 Set mosaic border
See description -
#61 Clean tile & tub
See description -
#62 Sand Drywall
See description -
#63 3rd coat drywall
See description -
#64 Set tile floor
See description -
#65 Cut door jambs for tile
See description -
#66 Set floor edging
See description -
Day 6
-
#67 Sand Drywall
See description -
#68 Touch-up drywall
See description -
#69 Clean up tile floor
See description -
#70 Mix Epoxy Grout
See description -
My favorite grouts
See description -
#71 Set grout
See description -
#72 Prep for paint
See description -
#73 Clean & tool grout
See description -
#74 Prime Walls & ceiling
See description -
#75 Caulk ceiling and edging joints
See description -
#76 Paint ceiling
See description -
#77 Shower trim
See description -
#78 Paint walls
See description -
#79 Caulk corners of tub surround
See description -
#80 Fill and caulk tub
See description -
#81 Grout floor
See description -
Day 7
-
#82 Replace Switches
See description -
#83 Install new GFI
See description -
#84 New breaker for GFI
See description -
#85 New Trap adapter for sink
See description -
#86 Install Vanity
See description -
#87 New shut-off valves
See description -
#88 Install sink faucet
See description -
#89 Set sink top
See description -
#90 Install base trim
See description -
#91 Connect Trap for sink
See description -
#92 Install heat vent and rest of base trim
See description -
#93 Install Light fixture
See description -
#94 Install Mirror
See description -
#95 Install toilet
See description -
#96 Accessories
See description -
#97 Shower rod
See description -
#98 Carpet Tuck
See description -
#99 Enjoy 😊
See description -